jurisdiction guide · florida

Miami Building Permit Review Times (Miami-Dade County)

In the Miami metro, building permits for unincorporated areas and many municipalities run through Miami-Dade County's building department (within the Department of Regulatory & Economic Resources). The County publishes the review window it works to.

Last reviewed June 5, 2026
headline figure
24h–10 biz-days initial plan-review window (Miami-Dade County)
what to know
Miami-Dade County targets initial plan review in 24 hours to 10 business days, with next-business-day expedited review available.
data source
Building — Plan Review & Expedited Programs
by the numbers

Miami-Dade permitting, the figures

The key published figures for this jurisdiction — each cited to its official source.

24 hrs – 10 business days
Initial plan review
varies by permit type and complexity
Source: Building — Plan Review & Expedited ProgramsBuilding — Plan Review
24 hrs – 10 business days
Re-review (Reworks)
after corrections are resubmitted
Source: Building — Plan Review & Expedited ProgramsBuilding — Plan Review
next business day
Expedited review
generally; per-discipline fee applies
Source: Building — Plan Review & Expedited ProgramsBuilding — Expedited Programs & Services
analysis

What the data shows

  • Miami-Dade County's building department states that initial plan review generally takes between 24 hours and 10 business days, depending on the permit type and project complexity (Miami-Dade County, Building — Plan Review).

  • Re-reviews of corrections (Reworks) fall in the same 24-hour to 10-business-day window once corrections are resubmitted.

  • For time-sensitive projects, the County's expedited review is generally returned the next business day for a per-discipline fee, with larger or more complex projects sometimes needing more time.

how permittable helps in miami-dade

Most delay accumulates before technical review

The data points to the same lever everywhere: most delay accumulates before technical review, in completeness and resubmittal cycles. Permittable's Permit Review Diagnostic checks your plans against applicable codes and common reviewer issues before you submit — so your package is more likely to clear on the first pass.

frequently asked

Miami-Dade permitting: FAQ

How long does plan review take in Miami?

For the unincorporated Miami metro and many municipalities, Miami-Dade County's building department says initial plan review generally takes between 24 hours and 10 business days, depending on permit type and complexity. Re-reviews of corrections fall in the same window.

Does Miami-Dade offer expedited plan review?

Yes. The County's expedited review is generally returned the next business day for a per-discipline fee, though unusually large or complex projects may take longer.

Is this the City of Miami or Miami-Dade County?

These figures are Miami-Dade County's, which handles building permits for unincorporated areas and many municipalities in the metro. The City of Miami operates its own building department with its own processes.

Sources

All figures on this page are drawn from Building — Plan Review & Expedited ProgramsMiami-Dade County — Department of Regulatory & Economic Resources (Building). County building-department guidance: initial plan review and re-review (Reworks) each generally take between 24 hours and 10 business days depending on permit type and complexity; expedited reviews are generally returned the next business day for a per-discipline fee. www.miamidade.gov/global/economy/building/plan-review.page. Specific tables, reports, and pages are cited inline with each figure above.

These figures are Miami-Dade County's published plan-review windows (Department of Regulatory & Economic Resources, Building) — initial review and re-reviews generally take 24 hours to 10 business days, and expedited review is generally next-business-day. They are review-step windows, not guaranteed total permit time, and apply to the County's jurisdiction; the City of Miami runs its own building department. Source: miamidade.gov.